Update, Oct. 21: Supervisors approved the item on Tuesday, Oct. 20, as part of the consent calendar. Acting as the board of the Contra Costa County Fire Protection District, they approved a request-for-proposals process for temporary quarters at Buchanan Field and determined that the Temporary Fire Station 9 Project is exempt from the California Environmental Quality Act. No contract has been awarded.
Contra Costa County supervisors are scheduled to consider a plan Tuesday, Oct. 20, for a temporary fire station at Buchanan Field Airport in Concord.
The interim station would support emergency operations while Fire Station 9 at 209 Center Avenue in Pacheco is demolished and rebuilt. The existing station dates to 1956. County documents describe a planned 15,400-square-foot replacement.
The temporary facility would operate around the clock on a paved lot at 200 Sally Ride Drive. It would include a 3,000-square-foot structure for two fire engines, a 1,500-square-foot modular building for firefighter living quarters, a storage container, fencing, parking and utility connections.
County staff estimate that demolition and reconstruction of Station 9 will take 17 to 24 months. The temporary site is intended to maintain fire and medical response coverage during that work.
The item before the Board of Supervisors would authorize a request for proposals, permit applications and lease negotiations with the county’s Airports Division. The board would also consider finding the temporary project exempt from the California Environmental Quality Act. Because the site is on airport property, staff also plans to begin a federal environmental review process under Federal Aviation Administration guidelines.
County staff said the state environmental exemption applies because the plan involves temporary facilities totaling less than 10,000 square feet, minor utility extensions and accessory structures in an urbanized area. The recommended action also calls for filing a formal notice of exemption with the county clerk and State Clearinghouse.
The temporary station would be paid for through the Contra Costa County Fire Protection District’s General Operating Fund. The proposal is still pending board action.
In its report, the district said failing to establish interim quarters could delay the main Station 9 project or reduce emergency fire and medical coverage for Pacheco and nearby service areas during construction.